Project Methodology 

Acknowledgment of tools 

Survey, Group discussion, Workshops, Interviews

Outcomes

Gathering space, Stimulating the community, Ownership of public Space

Oven Project.JPG
Involved Actors
Outputs
Period

Community Members : 50

Academic and Experts : 20

-Academic Staff in ASU and SI

-External Experts

-Students and Researchers of ASU and IUSD

-Community Members

-Skilled and Unskilled  Local Labor

-Representitive

​

An Oven

Cost of Project

8,000 €

Planning of Project :

May 2015 - Dec 2015

​

Implementation :

Planned : 3rd - 10th Dec

Actual : 3rd  - 10th Dec

Oven Project
Project Methodology 

Acknowledgment of community and municipality 

Survey, Group discussion, Workshops, Interviews, observation

Outputs

Seating Elements, New Shading Structure, Street Furniture. Greenery in the Street, Benches near Shops, Built-in Counters on the Walls

Street Project.JPG
Involved Actors
Outcomes
Period

Community Members : 120

Academic and Experts : 350

-Academic Staff in ASU and SI

-Students and Researchers of ASU and IUSD

-Community Members

-Shop owners

-Local Mosque Keepers

-Coffee Shop Owners

​

Awareness of the quality of public urban spaces 

Cost of Project

2,500 €

Planning of Project :

Jan 2015 - Aug 2016

​

Implementation :

Planned : Aug 2016

Actual : Aug - Oct 2016

Street Project
Project Methodology 

Acknowledgment of tools 

Survey, Group discussion, Workshops, Interviews

Outcomes

-Healthier and productive environment for children

-Participatory process including large number of participants

-Dynamic process required for construction

-Knowledge of implementing low cost material with its technicalities

School Project.JPG
Involved Actors
Outputs
Period

Community Members : 600

Academic and Experts : 300

-School staff (Director, Teachers, Care/Cleaning Staff)

-School Pupils

-Academic staff in ASU and SI

-Students of IUSD and ASU

-EZBET Community

-Ministry of Education (all responsible dep.)

​

Upgrading Shading Element, Courtyard, Greenery, Playground Areas

Cost of Project

18,000 €

Planning of Project :

Jan 2015 - Jul 2016

Implementation :

Planned : Aug 2016

Actual :

(Phase 1 & 2) Aug 2016 - Feb 2017

(Phase 3) Aug 2017 - now

​